2011 – Gulf of Mexico Transformer Replacement
- Installed rental transformer at platform.
- Drained and removed 5 MVA transformer at platform.
- Designed and fabricated new transformer deck for platform.
- Transported transformer deck offshore in two sections.
- Installed new transformer deck with safety ladder and handrails.
- Routed 5KV cables and installed junction boxes with splices.
- Installed new 5 MVA transformer on new transformer deck.
- Tested and Terminated new transformer.
- Energized new transformer and removed rental transformer.
- Completed Incident Free